Customer Enquiry
0151 832 5007
[email protected]
Emergency Helpline
(0)800 689 4803
24 hr / 7 days per week

Global shipping operations come to a holt

The Problem

Pleavin Power were contacted by the global shipping organisation after they had suffered from prime power failure whilst at sea, we arranged for our reactive response team to meet with the ship as it came into port to immediately commence an investigation and identify the route cause of the issues. We found heavy mechanical damage to the PMG rotor and stator after the PMG stator had come loose during operation, after completing further tests we also identified the machine was in desperate need of a mechanical and electrical overhaul before it could operate again.

The Solution

With overhaul out of the question due to tide times and shipping arrangements the client gave us a window of 72hrs to not only provide a solution but have the machine operational and ready to sail. After installing a different style of AVR to allow the generator to operate without the PMG we struggled with voltage control due to the resistance within the exciter so the decision was made to remove, rewind & re-install it within 24hrs. The team pulled together stripped the machine and had the Exciter in the oven that night before returning to reassemble, test and commission the generator with an hour to spare, fortunately, the client’s ship left the dock at noon Friday as planned.

A vessel we were providing Agency services for at Glasson Dock advised they were having trouble with one of their generators. We called Pleavin Power at 0800 in the morning and they were on the quay side three hours later whilst the vessel was tying up. Pleavin Power were able to diagnose the problem quickly. They then waited on standby for a decision from the ship owner and once received they immedi- ately returned and commenced work.They conducted the repair, which was initially quoted for a three day turn around in just over 36hrs, they worked non stop allowing the vessel to sail a day earlier than planned.From the first phone call to completion of the job the level of service has been second to non and Jack is clearly an absolute expert in his field and I will be cir- culating Pleavin Power’s details around the UK ship owners technical departments.
Ben
Global Shipping Operations

More Case Studies